POWERGRID Kala Amb Transmission Ltd (PKATL)
PROJECT DETAILS
Transmission system for Northern Region System Strengthening Scheme NRSS- XXXI (Part A)
Project specification
2.47 ckm of transmission line comprising LILO of 400 kV D/C Karcham Wangtoo-Abdullapur transmission line at Kala Amb (Himachal Pradesh) substation (on M/C towers)
630 MVA
400/220 kV GIS substation at Kala Amb
40% series compensation on 400 kV D/C line from Karcham Wangtoo to Kala Amb
Incorporation date
July 29, 2013
TSA date
January 2, 2014
Transmission licence issue date
September 4, 2014
Commercial operation date
July 12, 2017
Remaining TSA tenure
30.3 years*
*As on March 31, 2022
Key highlights FY 2021-22
PKATL has been allotted a project ‘Implementation of One no. 125 MVAr, 420 kV Bus Reactor at Kala Amb substation’ by Ministry of Power, GoI under Regulated Tariff Mechanism.
The project was notified on March 5, 2019.
PKATL was granted a separate transmission licence for the project by Hon’ble CERC vide its order dated March 22, 2022.
Target Availability (98%)
99.95%
FY18*
98.10%
FY19
Availability
99.90% 100.00%
FY20 FY21
99.12%
FY22
*July 2017-March 2018